Posts Tagged ‘Project Management’

From Predicting Agile to Agile Predicting The need for #NoEstimates fades when no estimate need be heavy-weight to be accurate.

The need for #NoEstimates fades when no estimate need be heavy-weight to be accurate.

Luke Woydziak

Luke Woydziak

Director of Engineering at EMC
Luke Woydziak
Luke Woydziak

Often Agile teams shun the notion of predicting a date. After all, for teams to make a prediction seems anti-Agile. There is even a #NoEstimates movement afoot. However, in business and in my experience giving some ballpark idea of when something will finish is not only beneficial but also often required.

Estimating accurately is surprisingly difficult as items have varying levels of complexity, certainty, size and dependencies. At #EMCDojo, we believe in providing a realistic date for the various stakeholders of the project. I want to show you a couple of methods we use to do that.

Armed with these methods, I think you will find that the need for #NoEstimates fades when no estimate need be heavy-weight to be accurate.

Let’s get started. We practice the weekly XP practice of an Iteration Planning Meeting. This is where the journey begins. During this meeting, we look at items on the backlog do an engineering analysis to scope, add detail, validate assumptions and address open questions. After such analysis, we Roman Vote on the point value in less that 30-seconds per item.

A common scale of 3-points is often used to point the story (as a team we selected Fibonacci, but in my experience as long as this is held constant, the discrepancies are negligible). We enter these values into Pivotal Tracker as it is a great tool for Agile projects in that it automates the velocity calculation.

The week progresses with pairs of engineers pulling the top priority stories off of the backlog and working them to completion (with unit/integration and system automated tests). The Technical Product Owner for the team will accept or reject the story depending on the actual functionality matching the desired behavior. During this time, Pivotal Tracker will automatically track and calculate velocity and various other metrics.

Below is an analysis screenshot from a live project in progress with the CPT team. You can view the project at https://www.pivotaltracker.com/n/projects/1518687

Analytics

 

As you can see, the tracker reported velocity was 6 points during the month of March 2016.

Velocity

 

While the velocity is interesting, the real value comes when you observe it over time. Again Pivotal Tracker will help you with this. By clicking on the velocity report, you can view a more detailed analysis.

VelocityReport

 

The most interesting data point in this screen is the standard deviation (σ). We use this measurement to establish a high confidence interval (CI) and a reasonable CI for a given prediction (assuming a normal distribution, which is arguably a very big assumption). If you are performing sophisticated business modeling, these are the numbers you can plug-in to model confidently with.

StdDev

One word of caution:

Velocity is extremely susceptible to gaming. So I would strongly recommend against using it to compare across teams. It is far more useful as a predictive element as opposed to a diagnostic element.

 

In our case, we extensively use both epics and releases. You can view and export both as spreadsheets.

Releases:

Releases

Epics:

Epics

 

When you have exported the data, you will get a spreadsheet like ours of releases (if you use releases, however, you can apply the same analysis to epics):

Screen Shot 2016-03-10 at 3.39.07 PM

 

Zooming in on the projected column show us the projected completion date as calculated by Pivotal Tracker:

projected

 

This is a raw prediction; you’ll need to adjust it with the standard deviation (σ) and some calculations. First, let’s calculate the σ adjustment to get a reasonable CI:

  1. Find the velocity (6)
  2. Find σ (2.2)
  3. Calculate the multiplication factor:
    1. v / (v – σ) = adjustment
    2. 6 / (6-2.2) = 1.579

You can apply this adjustment to the time duration from now until the raw prediction in days to get a reasonable CI projected date. For example (the date that we took this measurement was on 3/10/16): The first release “V1 Volume Manager Complete” was projected to finish 18-days from then on 3/28/16. 18-days multiplied by the adjustment is ~28-days. Add 28-days to 3/10/16 and you get 4/7/16.

You can apply the same to get a high CI by using 2σ:

  1. Find the velocity (6)
  2. Find the 2σ (4.4)
  3. Calculate the multiplication factor:
    1. v / (v – 2σ) = adjustment
    2. 6 / (6-4.4) = 3.75

Now you can begin to see how certainty affects the calculation. The breakdown is as follows:

  • Projected: 3/28/2016
  • Reasonable: 4/7/2016
  • High: 5/16/2016

You can add the calculations to an Excel spreadsheet with the following formula: “=(((Projected-Now)*Adjustment)+Now)”

Screen Shot 2016-03-23 at 9.28.47 AM

 

Zooming in you can see the new columns:

adjustmens

 

Now you have some options when communicating predictions and planning non-development, but related activities. With the assumption that this is a normal distribution, the σ and 2σ adjustments represent 68% and 95% respectively. I deliberately used reasonable and high in place of those numbers as I think there is reasonable doubt about regarding the shape of the distribution. Of course, you could manually track those numbers and increase measurement quality. Also, note this is very project specific.

Let’s see how this all worked out. The first release “V1 Volume Manager Complete” was renamed to “CF Summit Demo Day” and completed on 5/26/2016 versus the high confidence date of 5/16/2016.

finalFinish

 

We were 10-days off of the high estimate. So what happened? Well as with all projects we discovered additional items/stories and most likely it’s not a normal distribution.

So we learn velocity alone will only get you so far and doesn’t account for the incoming rate, but for most projects two-weeks variances is within the ballpark. We used this method to plan for presenting a demonstration of Legacy Application support functionality at the Cloud Foundry Summit 2016.

Likewise, you can use this method to make lightweight and reasonably accurate estimates and go from worrying about predicting Agile to making Agile predictions.

Can we do better?

In my next post, I’ll discuss another method, that while it is a bit more complicated and labor intensive, it can decrease the variance and is flexible enough for you to apply across projects easily.